Below is a list of current scheduled construction and lane closures in Montgomery County that could affect your commute.
Per MCDOT:
All work is performed weather permitting. Additional work hours and lane closure times may be necessary to expedite all phases of work and to keep all projects on schedule. Equipment used for construction may be disruptive. Real-time traffic information available at www.chart.maryland.gov or 1-855-466-3511.
Montgomery County
• US 29 (Colesville Road) from St. Andrews Way to Stewart Lane. Safety and resurfacing project. Single off-peak lane closures, weekdays, 9 a.m. to 3 p.m. and single and multiple overnight lane closures, Sunday through Thursday, 7 p.m. to 5 a.m. and Friday, 7 p.m. to 7 a.m. through winter 2022. (MO052)
• MD 97 (Georgia Avenue) from north of Gold Mine Road to south of Holiday Drive. MD 97 relocation project. Intermittent off-peak single and multiple off-peak lane closures, weekdays, 8 a.m. to 4 p.m. and overnight, Sunday through Thursday, 9 p.m. to 5 a.m. through year-end 2022. (MO746)
• Brighton Dam Road near MD 97 (Georgia Avenue). MD 97 relocation project excavation work. Off-road activity with intermittent off-peak single lane closures, weekdays, 7 a.m. to 5 p.m., and weekends, 8 a.m. to 4 p.m. through year-end 2022. (MO746)
• MD 185 (Connecticut Avenue) at Jones Bridge Road/Kensington Parkway. Intersection improvement project. Single off-peak lane closures on MD 185, weekdays, 9 a.m. to 3 p.m. and overnight, Sunday through Thursday, 8 p.m. to 5 a.m. and single off-peak lane closures on Jones Bridge Road, weekdays. 9 a.m. to 3 p.m. and overnight, 7 days per week, 9 p.m. to 5 a.m. through late summer 2023. (MO5935870)
• MD 190 (River Road) from MD 188 (Wilson Lane) to MD 614 (Goldsboro Road). Roadway improvement project. Single off-peak lane closures, weekdays, 9 a.m. to 3 p.m. and multiple lane closures, overnight, 9 p.m. to 5 a.m. through winter 2022. (XX2295376R)
• I-270 (Eisenhower Highway) from Interstate 70 to I-495 (Capital Beltway). Traffic congestion relief construction project. Intermittent off-peak single and multiple lane closures, weekdays, 10 a.m. to 3 p.m. and single and multiple overnight lane closures, Sunday through Thursday, 7 p.m. to 5 a.m. with intermittent temporary ramp closures with detours up to 24 hours a day through year-end 2022. (MO069)
• I-270 (Eisenhower Highway) northbound and southbound from MD 28 (Montgomery Avenue) to MD 189 (Falls Road). Traffic congestion relief construction project road widening and paving. Intermittent off-peak single and multiple lane closures up to 24 hours a day through year-end 2022. (MO069)
• I-270 (Eisenhower Highway) southbound from MD 121 (Clarksburg Road) to MD 119 (Old Hundred Road). I-270 acceleration lane expansion project. Single and multiple off-peak lane closures, weekdays 9:30 a.m. to 3:30 p.m. and overnight Sunday through Thursday, 7 p.m. to 5 a.m. and overnight Friday 8 p.m. to 4 a.m. Saturday morning through late summer 2022. (MO359)