Next Stage of Beltway Overpass Rehabilitation Includes 1 Month of Weeknight Beltway Closures

'

Next Stage of Beltway Overpass Rehabilitation Includes 1 Month of Weeknight Beltway Closures

Beginning at 9PM on Sunday, January 24, Maryland State Highway Administration contractors will begin setting new steel beams as part of the rehabilitation of the Seminary Road bridge over the Beltway, between Connecticut and Georgia Avenues.

This bridge rehabilitation includes replacing the bridge deck/driving surface and the steel framework below the deck. This next stage involves setting the steel beams for the future Northbound lane of Seminary Road. As crews will be working directly above the Beltway, the lanes below the steel work will need to be closed.

Crews will be closing lanes every weeknight between this Sunday (January 24th) and late February. Crews will close one lane at 9PM, two lanes at 10PM and three lanes at 11PM. Crews may also stop all four lanes of traffic in each direction for up to 15 minutes at a time. Maryland Route 200 (the Intercounty Connector), and Maryland Route 410 (East-West Highway) are good alternatives to use during these closures.

Featured Photo Courtesy of the Maryland State Highway Administration

'