Brick facades are currently nearing completion after a couple months of work on the exterior of the buildings. “As we progress with the brick façades around all sides of the new building, a variety of building styles, brick colors, heights and architectural features will emerge to give visual interest to the block and provide a different “identity” for each side. The brick work will continue through the summer and into the fall.”
Interior work is also ongoing. “We are busy with interior work as well. We are framing the walls on the second and third floors that will define hallways, apartment interiors and other spaces. Plumbing pipes for water and sanitary, mechanical ductwork and electrical work are all in progress. Interior work will move progressively up the building, and well into 2024.”
Underground utilities installation continues around the site. At the intersection of Halpine Road and Chapman Avenue we are working to complete new sidewalks and accessibility ramps, new traffic and pedestrian signals, and minor adjustments to curb alignments within that intersection. Wegmans isn’t expected to open until the end of 2024 or 2025.
Featured photo courtesy of Reimagine Twinbrook